Investor:   CEHIP s.r.o. and Pall Slovakia s.r.o.
Industry field:   Industry production - filters production
Location:    Vráble
Execution date: 06. 2014 - 01. 2015

Built up area:  3 900 m2 (hall + offices)

Activities:

Building permit documentation

Engineering for building permit

The site general contractor tendering

Execution design

Intermediation between the investor and the site general contractor

Regular inspection meetings

Construction time schedule monitoring

General contractor’s monthly execution approval

Handover and check of documentation provided by general contractor during the construction handover process

As built documentation

Building, roads and water operational permit

Photo documentation

 